-
2020 Bond ADA/Accessibility Project Overview
The 2020 Bond approved by voters allows for $33.8 million in main-level accessibility upgrades. Funds approved for accessibility will allow the 国产真实迷奸 to remove barriers at the main level of all school buildings district-wide.
What ADA/Accessibility projects are happening through the 2020 Bond?
Main-level accessibility/ project construction work includes upgrades to areas of the school that allow all people to reach the main entrance from the bus drop-off area and/or parking lot, access to essential programming; including an individual's classroom(s), the cafeteria, library, gym, and one or more accessible restroom(s).Projects were prioritized according to eligibility for federal and state funding and cost of each project and divided into two phases. SPED built environment improvements will happen concurrent with accessibility improvements at each site. The work takes place through two different phases.
2020 Bond ADA upgrades Phase 1
Phase 1 construction is underway at the following schools:
Lane, Mt Tabor, Vestal, Richmond, Scott, Beaumont, Irvington, George, Sitton, Chapman, Grout, Maplewood, MLC, Monroe/DaVinci, Sunnyside, Tubman, Winterhaven, Astor, Boise Eliot, Chavez, Chief Joseph, James John, King, Ockley Green, Peninsula, Rosa Parks, Sabin, Woodlawn, Bridger, Clark, Green Thumb, Kelly, Lent, Lee, Marysville, Rigler, Roseway Heights, Whitman, Woodmere.Phase 1 work is expected to be substantial complete by late spring 2024.
2020 Bond ADA upgrades Phase 2
Phase 2 work will begin in the summer of 2024 and will take place at these schools:
Alameda, Applegate, Beach, Beaumont, Beverly Cleary Fernwood, Beverly Cleary Hollyrood, Clarendon, Kenton, Laurelhurst, Rose City Park, Sacajawea, Vernon, Ainsworth, Bridlemile, East Sylvan, Forest Park, Gray, Hayhurst, Skyline, West Sylvan, Arleta, Atkinson, Buckman, Cleveland, Creston, Glencoe, Hosford, Lewis, Marshall, Woodstock, Abernethy, Capitol Hill, Duniway, Jackson, Llewellyn, Markham, Rieke, Sellwod, Stephenson, Ida B Wells, Holladay Center & Youngson.Phase 2 work is expected to be substantial complete in early 2025.
ADA project scope of work
Work at each site varies, but most include some or all of the following modifications:Parking lot striping for accessible stalls
Providing accessible walkways to accessible entryways
Adding ADA door operators at main or accessible entries
Exterior handrails at ramps and stairs
Exterior ramp construction
Renovating restrooms
Replacing (e) sinks with accessible sinks
School interior ramp construction
Portable classroom entry modifications
Installation of assistive listening devices
Installing lifts at theater stages
Interior handrail installation
New accessible door hardware in classrooms and common areas throughout schoolsIn addition to these improvements, SPED improvements are also happening concurrently. These include dimmable LED lighting in SPED classrooms and larger single-user restrooms suitable for special education students. Learn more at the 2020 Bond SPED improvements webpage.
-
ADA BAC Project Status Report
BAC Infrastucture: ADA Status Report Oct 2024For more information about PPS Bond ADA projects, please email schoolmodernization@pps.net