• 2020 Bond Mechanical Systems Upgrades

    The 2020 PPS School Improvement Bond provides $75 million to replace or repair the highest priority mechanical systems (heating, cooling, and ventilation) in schools throughout the 国产真实迷奸. This funding will also be used to address smaller mechanical projects.

    Mechanical deficiencies are PPS’ largest facility need, with dozens of schools having major mechanical system components in critical condition. 

    Detailed assessment by professional mechanical engineering firms will be necessary to determine how to solve a failing or poor performing system. Some projects will require full system replacement, while others will require only targeted improvements.  These funds provide the budget to complete approximately 15 of PPS’ highest priority sites.

    Mechanical Systems Update for September 2024 - Lent K-5 School
    Heating unit in Lent Classroom
    This is a complete replacement and upgrade of an existing aging mechanical system at Lent K-5 School with new independent room control and filtered air system. It began construction in late spring 2024 and is anticipated to be complete in the Fall of 2025.

    Mechanical Systems Update for September 2024 - Bridger/Creative Science School
    New Boiler system at Bridger
    This is a complete replacement and upgrade of an existing aging mechanical system at Bridger/Creative Science School with new independent room control and filtered air system. It began construction in late spring 2024 and is anticipated to be complete in the Fall of 2025.

    Mechanical Systems Update for September 2024 - Kelly Elementary School
    Bridger new boiler

    This is a complete replacement and upgrade of an existing aging mechanical system at Kelly Elementary School with new independent room control and filtered air system. It began construction in late spring 2024 and is anticipated to be complete in the Fall of 2025.