Harrison Park Middle School Conversion
The 2020 Bond is funding the conversion of Harrison Park K-8 to a Middle School. While not a full modernization, the work significantly upgrades the school's facilities. In addition, Harrison Park already has a number of great features that will make for a good middle school experience. Construction on the school is designed in a way to minimize the impact on students and staff. Middle school students started attending Harrison Park in the 2023-24 school year.Current Construction 2024-25
- Renovating four science classrooms.
- Upgrading the auxiliary gym.
- Upgrading the Dance studio.
- Adding a new Art Classroom.
- Flooring & ceiling work.
Construction 2023-24
- Construction took place on the STEAM Lab, science classrooms, art room, some Special Education spaces, and extended learning spaces.
- Crews added a brand-new HVAC system - Harrison Park now has air conditioning and filtered air! Additionally, new fire sprinklers were added.
- A new secure entryway vestibule at the entrance for added safety & security.
- 12 all-user bathrooms were completely renovated with three being ADA compliant.
- Seismic upgrades included adding new sheer walls and replacing a URM wall in the Library, Corridor & Science Rooms with a new seismically strengthened wall.
- Upgrades to the Main Gym.
- New technology upgrades in all classrooms.
2023 Construction update flyer
View 2023 Construction update flyer
Español |Ti?ng Vi?t | Русский | Soomaali | 中文Construction impacts on the school during the 2024-25 school year
- Safety is our number one priority. Construction activity is separated from the school environment!
- Construction in certain areas of the building will be safely closed off with barriers from the functioning learning environment. Students and staff will not come in contact with construction activities.
- Construction dust and debris are safely contained in sealed-off areas and will not enter the school.
- Classrooms being used this year will not be impacted by construction.
- Students should enter through the main entrance on 87th. There will be temporary signage inside and outside the building so everyone can find where they’re going.
- All exterior construction areas are completely fenced off with privacy screening to limit distractions.
- The team is making every effort to minimize disruption to the learning environment. Although there will be some construction noise, the loudest activities are scheduled to take place outside of school hours.
- There will be exposed ceiling areas in the hallway to the Cafeteria and some classrooms in that area will be closed off in order to complete their work.
- The floors throughout the school are not finished. This will be one of the last projects the crews will complete before the entire job is finished.
- Some sections of ceiling will be exposed, and temporary lighting will be used.
- There will be temporary walls placed in some locations for student safety.
Work completed prior to 2023
- Upgrades and refreshed finishes in the front lobby, main corridor space, & cafeteria space
- Addition of interior and exterior security cameras
- Covered bike rack at the front of building
- City-required street improvements and garbage enclosure and south parking lot updates.
Harrison Park Existing Features:
Harrison Park offers many features that made its conversion to a middle school a good option. The structure is in good condition and a new seismically strengthened roof was recently completed in 2021. The school also has two gyms, a large dance studio, a unique theatre/auditorium and a dedicated cafeteria. It also has a spacious library, interior courtyards, greenhouse and a robust school garden.
-
CAPACITY BAC PROJECT STATUS REPORT
BAC Infrastructure: Capacity Status Report Oct 2024For more information about this project, please email schoolmodernization@pps.net