2020 Bond Roof Projects
The 2020 PPS School Improvement Bond provided $65,700,000 to address PPS roofing needs that are currently critical or will become critical over the next several years. Roof replacements often include ancillary scope of work including roof level seismic improvements, additional building insulation, replacing outdated rooftop equipment, and other upgrades.
2020 Bond completed roof projects:
Ainsworth Annex Completed 2022
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
Ceasar Chavez Completed 2022
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Duniway Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
Glencoe Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
Markham Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Meek Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.MLC Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
Reike Completed 2023
Roof/Seismic w/ Fall Protection - Complete roof replacement with sheathing upgrade and improvements on the entire main building roof. Cleaning and elastomeric recoating of the gym roof, complete roof replacement and insulation of the annex building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Richmond Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Skyline Completed 2023
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Vernon Completed 2024
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
West Sylvan Completed 2024
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.Winterhaven Completed 2024
Roof/Seismic w/ Fall Protection - Partial re-roof of the school building. Work included replacing skylights, flashings and sheet metal, with seismic upgrades including parapet bracing, strengthening roof decks and improving roof to wall connection. All portions of the roof will have OSHA -compliant fall protection equipment incorporated into the final design.
-
ROOF PROJECTS BAC STATUS REPORTS
BAC Infrastructure: Roof Projects Status Oct 2024For more information about PPS roof/seismic projects please email: schoolmodernization@pps.net