Volunteer Projects
Annually, Facilities & Asset Management (FAM) receives numerous requests for volunteer projects to improve and enhance PPS school buildings. These volunteer projects must be closely managed to achieve the desired outcomes of the district’s design standards. FAM has identified a number of issues that require careful consideration before approving any volunteer projects.
Project Initiation
• All volunteer efforts must be initiated using FAM’s Project Development Request Form; please see the Project & Construction Management main web page.
• FAM requires a 10-day review period from initiation date to project approval for any volunteer project.
• Meet with your assigned project manager to discuss the anticipated scope of work, budget and schedule for your volunteer project.
Design Requirements for Volunteer Projects
Work with your project manager to determine if the scope of the project requires a licensed professional (i.e. Architect/Engineer).
Familiarize yourself with the 国产真实迷奸 Design Standards and ensure your project meets these requirements.
Secure a volunteer or paid professional to produce drawings and documents to a professional level and sufficient to meet PPS and City of 国产真实迷奸 requirements.
a) The design documents should tell the full story of the project. Documents should make it clear what is new work, vs. what is existing work. They should provide enough detail to indicate specifically what is being installed/built, what materials are being used, and how it should go together. This may include both demolition and construction plans. It will likely require plans, elevations, sections, details and specifications. Work with your Project Manager, who will coordinate with the Design, Permitting and Document Control Coordinator to help you get clarity of what will be required for your specific project.
Determine if your project requires a building or site development permit. If it does, research the permitting requirements for project. Your Project Manager will enlist the support of the 国产真实迷奸 Land Use and Code specialists in research of existing conditions and City requirements.
Familiarize yourself with all required codes. Consider Building Codes, Accessibility Codes, Land Use Code, and any others as applicable.
Your project will need to go through the 国产真实迷奸 Design Review Process. For most projects, multiple rounds of review are required and each round can take up to 2 weeks. Ensure you provide enough time in your schedule for this process. The earlier you engage in this process, the faster and smoother this process can be. The 国产真实迷奸 can help you with finding the right location, potential risks to consider, lessons learned from past similar projects, etc.
PPS Design Review Approval is required prior to permits submitted for or any work being done on-site. The City of 国产真实迷奸 building permit application will be signed by the Document Control Coordinator once the PPS Design Review process is complete.
Volunteer Requirements
Volunteers shall consult with PPS Project Manager about the appropriate hold harmless and background check requirements for a particular project.
Fundraising & Budgeting
There are a variety of 国产真实迷奸 and non-国产真实迷奸 fundraising resources available to volunteer groups. Fundraising efforts shall be coordinated with the PPS Project Manager to ensure they are not competing with other 国产真实迷奸 efforts. The PPS Project Manager will work with volunteer groups to ensure that a comprehensive project budget has been prepared and that all project funding is available prior to the start of work.
Project Closeout Requirements
Upon construction completion, you will need to provide complete closeout documents. This will include among other possible requirements:
1. One hard copy and one electronic copy (both .pdf and original CAD/Word documents) of as-built drawings/specifications.
2. O&M manuals including: (a) Contact information for all parties (Primary Volunteers, Contractor, etc.) and (b) Specific products (brand, serial number, colors, etc.) being installed
3. Warranties
4. Final close out of city building permits.
5. Other specific project requirements. Work with your Project Manager to know what may be additionally required for your project.